Welsh Energy Customers Share Rising Cost of Switching Off Wind Farms as Britain’s Bill Tops £1.5 Billion
Households and businesses in Wales are helping to fund the rising cost of reducing wind farm output when Britain’s electricity network cannot carry the power to where it is needed.
Figures reported by The Times on 5 October, citing Octopus Energy’s Wasted Wind tracker, put the Britain-wide cost of curtailing wind generation and paying for replacement electricity at £1.51 billion so far in 2026. That exceeds the £1.47 billion recorded throughout 2025.
Of the latest total, £1.28 billion was spent on gas-fired replacement generation. The headline figure therefore includes substantially more than payments to wind farms to reduce output, and should not be presented as the cost of switching off turbines in Wales – however, according to the Times, the overall UK bill is rising
A current, verified Wales-only total could not be established from the sources reviewed. However, Welsh customers contribute through energy bills to the costs of balancing the wider electricity system, including constraints elsewhere in Britain.
The lack of a separate Welsh figure has previously been raised in Parliament. In September 2025, Plaid Cymru peer Lord Wigley asked the UK Government how much had been paid to wind farm operators in England, Scotland and Wales in each of the preceding five financial years.
The Government’s answer directed him to National Energy System Operator data, explaining that its monthly reporting grouped England and Wales together, with Scotland reported separately. It did not provide the requested Wales-only breakdown.
Wind farms can be instructed to reduce generation when electricity would otherwise exceed the safe capacity of a particular part of the network. NESO describes these physical limits as constraints: bottlenecks that prevent power moving freely between regions.
This means that available wind energy can be curtailed even while electricity is needed elsewhere. To maintain supplies, the operator may pay another generator on the other side of the bottleneck to increase production.
NESO gives the example of reducing wind generation in the north while increasing gas generation in the south. The problem is the location of generation and the capacity of the connecting network, rather than simply having more electricity than Britain needs.
The operator says constraint payments have, to date, been the most cost-effective way of keeping the system secure. It is also working on network reinforcements and other measures to reduce the need to curtail renewable generation.
For Wales, these costs strengthen the case for coordinating new renewable developments with the infrastructure needed to use their electricity.
Concerns about the capacity of the electricity network have previously been raised in the Senedd.
During a debate on Wales’s renewable energy needs on 19 March 2025, Carolyn Thomas said:
“At present, the national grid cannot cope after years of underinvestment and is in need of major renewal, which will take years.”
In a March 2026 update, the Welsh Government highlighted Contracts for Difference awards for the 755MW Awel y Môr offshore wind project off North Wales and the 100MW Erebus floating wind project in the Celtic Sea.
The statement also recognised the grid as a priority for the sector and outlined work with NESO on strategic energy planning. The funding awards concern future electricity generation; they are distinct from payments made when existing generators are instructed to reduce output.
The rising national bill illustrates the financial consequences when electricity generation and network capacity do not develop together. For Welsh consumers, the immediate issue is their contribution to those shared system costs. Establishing how much is paid specifically to wind farms in Wales would require a separate, clearly defined breakdown of payments by generating site and reporting period.
Sources